Pressure systems under PSSR 2000: written schemes and examinations explained

A pressure system must have a written scheme of examination, drawn up or certified by a competent person, before it is put into use. How often it is examined is set by that scheme, not by the Regulations.

Every check and its frequency

Covers users of installed pressure systems, for example steam boilers, air receivers and compressed air systems, and owners of mobile systems, in England, Scotland and Wales.

CheckHow oftenBasisStatusSource
Have a written scheme of examination and review it at appropriate intervalsBefore the system is operated; reviewed at appropriate intervals (no fixed frequency)Regulation 8 of the Pressure Systems Safety Regulations 2000. Required by law: the system must not be operated without a written scheme of examination.LawThe Pressure Systems Safety Regulations 2000, regulation 8
checked
Examination in accordance with the written schemeWithin the intervals set in the scheme (set by the competent person, not by the Regulations)Regulation 9 of the Pressure Systems Safety Regulations 2000. Required by law; your written scheme, not the Regulations, sets the examination interval.LawThe Pressure Systems Safety Regulations 2000, regulation 9
checked

No fixed interval is set in the Regulations; your competent person sets one in the written scheme. Do not run the system beyond the next-examination date on the most recent report.

What it is about

The Pressure Systems Safety Regulations 2000 apply to systems that contain or convey a fluid under pressure, including steam boilers, compressed air receivers and their pipework. If one fails, stored energy can be released suddenly and cause serious injury.

Rather than fixing an inspection interval, the regulations require a written scheme of examination, drawn up or certified by a competent person, setting out what has to be examined and how often.

Examinations are covered by the written scheme. Separately, the regulations require the system to be properly maintained in good repair, so routine maintenance by your own staff or a contractor is also needed.

The checks one by one

Have a written scheme of examination and review it at appropriate intervals

Before the system is operated; reviewed at appropriate intervals (no fixed frequency) · Law

Regulation 8 of the Pressure Systems Safety Regulations 2000. Required by law: the system must not be operated without a written scheme of examination. Source, last checked .

Examination in accordance with the written scheme

Within the intervals set in the scheme (set by the competent person, not by the Regulations) · Law

Regulation 9 of the Pressure Systems Safety Regulations 2000. Required by law; your written scheme, not the Regulations, sets the examination interval. Source, last checked .

Whose duty it is, and who can carry it out

For an installed system, the user; for a mobile one, the owner. They must have a written scheme in place before the system is operated, and ensure a competent person carries out examinations within the intervals it sets.

What to record

Retain the written scheme. Following each examination, the competent person has to provide a written, signed and dated report within 28 days, or before the next examination date if that comes first.

How to run it well

  1. Make a list of all pressure systems on site, compressors and air receivers in workshops and plant rooms included.
  2. Never run a system beyond the next-examination date on its last report.
  3. Revisit the written scheme if the system is altered or used in a different way.
  4. Store maintenance records together with the examination reports.

Building types it applies to

Pressure systems is included in our compliance calendar for 1 of the 5 building types on the site. Every calendar puts it next to the other checks that building usually needs.

Managing it in software

A CAFM system can schedule these checks, remind the person responsible, and file every certificate or log entry against the asset, keeping the evidence together for an inspector or insurer. The table sets out what each product states in its documentation.

SoftwareCompliance certificates and expiry trackingPlanned maintenance (PPM) schedulingSFG20 maintenance libraryContractor portalQR or NFC asset tags
JoblogicYesYesYesPartlyYes
InfraspeakYesYesYesYesYes
PlanonPartlyYesYesPartlyYes
ConcertoYesYesYesYesYes
Service Works GlobalPartlyYesYesPartlyYes
MaintainXPartlyYesNot confirmedPartlyYes
SnapfixYesYesNot confirmedPartlyPartly

For the products ordered for this job, see the the compliance software shortlist, or read what planned preventive maintenance is.

Common questions

How frequently do pressure systems need examining?

Within the intervals the written scheme of examination sets. No fixed interval is given in the regulations.

Who prepares the written scheme?

It is drawn up by a competent person, or certified by one as suitable.

By when must the examination report be issued?

Within 28 days of the examination, or before the next examination date if that comes first.

Are examination and maintenance the same thing?

No. The examination checks the system against the written scheme, while maintenance keeps it in good repair. Both are required.